Item Restricted to University of Alberta Users

Log In with CCID to View Item
Usage
  • 89 views
  • 1 download

Cover Design of a Backfilled Open Pit Based on a Systems Approach for a Uranium Mining Site

  • Author(s) / Creator(s)
  • Relocation into the Lichtenberg open pit mine of about 110 million m3 of sulfide-bearing and ARD-generating waste rock piled up on the surface is the most important and cost-intensive single surface restoration project conducted by WISMUT GmbH at the former Ronneburg uranium mining site. The waste rock comprises for the most part Palaeozoic shales, limestones and diabases with pyrite contents of up to seven per cent. Waste pile relocation began in 1992 and is scheduled to be completed by 2007. The approach used for relocation has been extensively described elsewhere (Jakubick et al, 1997; Hockley et al, 1997; Chapman et al, 1998; Paul, 2003). Following completion of the backfill that will be up to 60 m above the initial ground level, a dry cover will be placed on top of the backfilled mine wastes. The area to be covered amounts to about 220 ha. Design planning for the final cover placement of which is to begin in 2004 had to be based on a comprehensive cost-benefit analysis over and above compliance with legal requirements. The crucial question to be answered in this respect was to determine – in addition to the expenditure required to ensure reuse, radiation protection and soil protection – the extent to which additional time, effort and money were justified in order to minimise contaminant release from the unsaturated portion of the backfilled pit contributing to total releases into the ground water and possibly achieve savings in long-term operating costs for the on-site water treatment plant. Optimisation was based on contaminant balance modelling for the entire site reproducing dominant physical and geochemical processes. Among the specifics underlying the cover design is that contaminant release from the backfilled open pit must not be considered independently of that from the adjacent flooded underground mine and that a major part of the backfilled open pit will also be submerged. Following weighing of cover-related short- and long-term costs it was found that higher construction costs for the various cover options will not be offset by cost savings in the long-term water treatment. As a consequence of pit flooding, even a costly multiple cover including an impermeable layer will only insignificantly impact on concentrations and loads at ground water spill over points. As a result of comprehensive studies and investigations, a combined cover of cohesive soil material from on-site excavation overlain by a 0.4 m thick storage layer to restore natural soil functions for revegetation was derived and submitted for approval. Together with hydraulic measures, this approach is to meet any requirement in terms of radiology, water protection, stability, erosion protection, and reuse.

  • Date created
    2003
  • Subjects / Keywords
  • Type of Item
    Article (Published)
  • DOI
    https://doi.org/10.7939/r3-xg82-7002
  • License
    Use of this product is restricted to current faculty, staff, and students of the University. It is the responsibility of each user to ensure that he or she uses this product for individual, non-commercial educational or research purposes only, and does not systematically download or retain substantial portions of information. Users may not reproduce or redistribute unprocessed/raw data portions of the data to any third party, or otherwise engage in the systematic retransmission or commercialization of the data.