  • Spring 2012

    Hong, Jangmi

    a special purpose simulation tool called ISP (integrated simulation-based planning). The ISP’s main framework is a simulation-based network analysis based on a precedence diagram method. The ISP tool application has been demonstrated with a hypothetical road construction project. The approach is

    Cost and schedule integration can improve efficiencies in construction planning and control since they are key constraints in project delivery and closely related. This research provides a framework for cost and schedule integration, and transforms the model to simulation-based planning in which

    the uncertainties of project cost and schedule are evaluated through computer simulation. This has been achieved through explicitly incorporating risk, resource, and detailed operation into a work-packaging model. The developed framework has been implemented in the Simphony.Net modeling environment as